Furniture is a programme item, not a finishing touch.

Furniture is where a good fit-out programme is most often lost. Lead times run in months, approvals take weeks, and the move date does not move.

We procure, consolidate, deliver and install furniture against the construction programme, and where a bespoke item is required we manufacture it in our own workshops.

Contemporary furniture arranged in a finished interior

Scope

What the package covers.

Scope

  • Furniture specification and standards review
  • Procurement against approved samples
  • Bespoke items manufactured in our workshops
  • Consolidation and storage before delivery
  • Delivery, unpacking and installation
  • Waste removal and recycling of packaging

What we manage

  • Lead times mapped against the move date
  • Sample approval and ergonomic trials
  • Loading dock, lift and access bookings
  • Floor-by-floor installation sequence
  • Snagging, adjustment and replacement
  • Asset schedule and warranty documentation

Interfaces we resolve

  • Power and data at desk positions
  • Floor box locations against the furniture plan
  • AV positions in meeting rooms
  • Existing furniture to be retained or reused
  • Landlord protection and delivery restrictions
  • Building rules on out-of-hours delivery

Control

Where the risk actually sits.

Order dates are milestones

Each order date is set back from the move date and tracked as a programme milestone, so a slipped approval is visible immediately rather than at delivery.

Consolidate before site

Deliveries are consolidated and checked before they reach the building, which keeps damaged or wrong items out of a live installation week.

Install to a floor plan, not a pile

Every item is labelled to its position and installed floor by floor against the approved furniture plan.

Before pricing

What we need to see.

Send what exists today. We will tell you what is still required rather than price around the gaps.

  • Furniture specification or existing standards
  • Headcount and layout plan
  • The move date and any phasing
  • Existing items to be retained
  • Building delivery and access restrictions
  • Budget range for the furniture package

Questions

What clients ask about this scope.

Discuss an office project

Tell us about the floorplate and the date.

Tell us the building, the area, the scope you expect to hold and the date the business needs to move. We will set out how the programme would run and what has to be resolved first.