Commissioning engineer testing installed building services

MEP case study · Leisure

Themed Attraction — Services in Sculpted Geometry

Riyadh, Saudi Arabia · 2024 · Main contract

Scope

MEP coordination with architectural elements

Zones

Multiple themed environments

Programme

16 months

Interfaces

Ride systems, GRC/GRP, lighting, fire, HVAC

Services routed through sculpted composite geometry with no repeating grid — coordination carried out in the model because there were no flat surfaces to measure from.

01Coordination

Services routed through geometry with no repeat

Every duct, sprinkler drop and cable route was placed inside the sculpted composite model, so penetrations were cast into panels in the workshop rather than cut on site.

  • Laser survey of structure before composite panels were modelled
  • Service penetrations cast into panels at manufacture
  • Ride-system clearances treated as fixed no-go volumes
  • Access hatches designed as part of the themed surface
Coordination model showing services routed through complex geometry
Coordination — penetrations decided in the workshop, not on site

02Plantroom

Back-of-house built to carry the show

Plant and distribution were sized for peak guest load and show conditions, with routes kept entirely out of guest sightlines.

  • Plant sized for peak occupancy and show-effect loads
  • Distribution routed behind themed surfaces with maintained access
  • Vibration and acoustic isolation for plant adjacent to guest areas
  • Riser and containment set out against the surveyed structural grid
Service riser with neatly bracketed pipework and containment
Distribution — capacity and access held behind the show surface

03Commissioning

Tested against show conditions

Systems were commissioned under simulated show and peak-occupancy conditions, with fire, smoke control and effects interlocks tested together rather than in isolation.

  • Smoke-control and cause-and-effect testing with effects running
  • Cooling verified at peak occupancy and full lighting load
  • Show-control and BMS interfaces proven end to end
  • Snagging closed zone by zone ahead of the public opening
Control room screens showing systems status during commissioning
Commissioning — proven under show conditions, not idle conditions

04Handover

Opened on the fixed public date

Operations received a documented, tested building with maintenance routes that survive the theming — the difference between a set and an operating attraction.

  • As-built model including concealed service routes behind theming
  • Maintenance access map issued with the O&M package
  • Operator and technician training delivered before opening
  • Aftercare team retained through the first operating season
Completed themed environment walkthrough at handover
Handover — an attraction that can be maintained, not just opened

Services that close the ceiling,
and the programme.